Two electricity projects completed in Weilheim

In Weilheim an der Teck, at the foot of the Swabian Jura, Josef Rädlinger Ingenieurbau GmbH's network construction division has carried out two electricity projects on behalf of Netze BW in March and April.

The order was received in late February and included the wiring of parts of an industrial area and a low-voltage overhead line need of renewal, including the service connections in the residential area concerned.

In total, network construction teams created about 600 metres of route for the main power supply and almost 20 service connections. In addition, cable-conduit-protection systems and cable distribution cabinets were installed at the same time. In parallel with construction of the power lines, the network construction team also carried out repair work in the town's streets.

After the cables were installed, the power connections of the customers were linked to the mains and the surface works in the area of the lines completed on time, and the roads opened to traffic.


Corporate Video

 

News-Archiv

29.01.2015 New junction, and additional noise-reduction measures for the A99

In March 2014 Rädlinger Bauunternehmen began laying the Aschheim junction on the A99. During the morning rush hour, the area was experiencing overloading of...[more]



26.08.2014 Gas pipes set up to Stammheim prison and Heimsheim prison

On behalf of NETZE-BW (an EnBW company) founded at the beginning of the year, the network construction department at Josef Rädlinger Ingenieurbau GmbH undertook to set...[more]



11.03.2014 Challenging large trench sewer construction

On the construction site of the B464 Sindelfingen-Renningen (lot 13; section 03), Rädlinger Bauunternehmen was entrusted with the construction of a sewer with storage...[more]