New major contract, BAB A3 Frankfurt - Nuremberg motorway

Josef Rädlinger Bauunternehmen GmbH has been awarded a new major contract for the A3 motorway. The widening of the BAB A3 Frankfurt-Nuremberg motorway to 6 lanes from the Baden - Württemberg state boundary up to Würzburg - West junction, from construction chainage 267+100 to construction chainage 278+020, will be carried out by the Rädlinger / Bögl JV.
Rädlinger will have overall technical control, its JV partner Max Bögl will be responsible for the commercial side.

The following construction work was carried out by Rädlinger:
Topsoil approx. 115,000 m²
Total earth moving approx. 320,000 m³
Frost protection course approx. 180,000 m³
Dismantling old carriageway approx. 230,000 m²
Asphalt base course, binder and mastic asphalt, each approx. 340,000 m³
The construction period is scheduled from March 2010 to December 2011, the employer is  Autobahndirektion Nordbayern, Würzburg office.


Corporate Video

 

News-Archiv

28.10.2014 Young entrepreneurs visit the Raedlinger company group

On 27th October the "Junge Unternehmer Niederbayern-Oberpfalz e.V." (club of young entrepreneurs from the lower Bavaria and upper Palatinate region) of Germany met on...[more]



04.07.2016 The missing piece to the puzzle: Rädlinger has started building construction

With its new building construction department, Rädlinger has developed one of the last fields still to be covered in the construction branch. After the decision was made...[more]



29.04.2015 Two electricity projects completed in Weilheim

In Weilheim an der Teck, at the foot of the Swabian Jura, Josef Rädlinger Ingenieurbau GmbH's network construction division has carried out two electricity projects on...[more]