Inauguration of Vilshofen station with wheelchair access

The new central platform at Vilshofen station was officially put into operation at the start of February. With the successful implementation of the project “Station with wheelchair access” in Vilshofen, Rädlinger Ingenieurbau in Vilshofen demonstrated its organisational and improvisation skills.

The development of the central platform with a length of 280 m took place from May to December on one side at a time. For the development of the central platform for wheelchair access, it was raised above the top of the rails and connected to the underpass with a lift. The construction project also included the dismantling of the old platform roof and its replacement.

For the implementation of the project, the respective track on the side of the construction site was closed for a certain period; rail traffic continued on the other track. Therefore, on the one hand, access for the passengers to the platforms had to be possible at all times and, on the other hand, the supply of materials and machinery constantly had to be re-planned. In order to reach the relevant platform under construction, close cooperation with the station master was necessary.


Corporate Video

 

News-Archiv

16.05.2011 Schönthal bypass opened to traffic

Following completion of the construction site at chainage 2400, Schönthal bypass, in May the new east-west axis was opened to traffic. The application for construction...[more]



17.06.2014 50th anniversary of the company in "Rädlinger music hall"

The Rädlinger family extended an invitation to attend music hall on two evenings in June. The 50 years of company history were celebrated copiously together with...[more]



25.05.2015 Energy supplier N-ERGIE visits Rädlinger

Last week, representatives of the energy supplier N-Ergie visited the Rädlinger Group to learn more about the head office and corporate departments. The network...[more]