Visit to the B20 trunk road and Eschlkamer Straße construction sites

During a visit to site on 1 August, local politicians, representatives of the state building control office and employees of Rädlinger and Bögl examined construction progress on the B20 construction sites near Weiding and Eschlkamer Straße in Furth im Wald.

Earthworks have been underway since April on the B20 near Weiding, as preparation for the planned asphalting in the spring of 2013. Approx. 85,000 m³ soil has been moved along the 3.7 km section of road. It is estimated that around 25 000 tonnes of asphalt will be required. The earthworks around Weiding were completed at the end of August, so that the existing diversion can be removed at the end of September – two months earlier than planned.

The second construction site visited was the cut and cover site in Eschlkamer Straße, which is being built by a JV of Rädlinger and Bögl. 200 of the 537 metre long cut and cover has already been covered. Completion of the cut and cover section is scheduled for the summer of 2013.

 


Corporate Video

 

News-Archiv

10.12.2013 Redesign of Steinmarkt in Cham

There are doctor’s practice, pharmacies and a number of shops at Steinmarkin the old town in Cham. Accordingly, the square is much frequented by pedestrians and motor...[more]



19.05.2009 Open day at the Rädlinger Vocational Training Center

On 16th May 2009 there took place for the first time an open day at the Schwandorf Vocational Training Center. Department manager Rupert Schichtl was pleased that, as...[more]



15.04.2014 Annual construction contract with REWAG

House connections, fault clearance, pipe construction – the annual construction contract between the Network Construction Department and REWAG in Regensburg covers a...[more]